Fall on Smokeshire Road

When Tony, our contractor, first checked the availability of the roof trusses we were going to use, he was told there was a two-week lead time. Then, when he called to order them, the lead time had changed to 6 to 8 weeks! He was able to find another source, but those trusses, being somewhat different, couldn’t be ordered until the structural engineer cleared them.

The new trusses were cleared and ordered, but that caused a delay of about 2 weeks. During that time, the view of the house changed very little, but fall continued to transform the countryside. Here is a gallery of fall on Smokeshire Road. Click on any of the images to enlarge.